Austria's cutting-edge-thermal power plant is already supplying electricity and district heating. Investment sum totals € 550m.

Verbund Starts Styrian Power Plant / Picture: © Flickr

The production of environmentally friendly district heating in the new Verbund thermal plant at Mellach has been taken up. This combined cycle power plant at the same time generates electricity and heat, which is utilised in the households, offices and large industrial complexes of Graz.
For several weeks, tens of thousands of households in the district heating network of Graz…